Project Management Friendly Assisted Living Facility Case 7 Questions 1. Page 263-265, Case, Friendly Assisted Living Facility Case 7 Answer Questions 1-5, Place use pdf format, 2. Page 266-267, Case, Peak Lighting, Inc. Answer Questions 1-4, Place use pdf format, 3. Page 284-287, Case, Friendly Assisted Living Facility Case 8 Answer Questions 1-5, Place use pdf format, 4. Page 288-289, Ivory Tower System Answer Questions 1-3, Place use pdf format, 2 63
C AS E
C
A
Friendly Assisted Living Facility Case7
It is now just 4 months until the Assisted Living Facility
program is scheduled to be completed. The team is excited
because they can watch the construction of the facility
and feel they are moving toward the end of this program.
Every week since construction began, the construction
project manager, Kyle Nanno, has been holding a meeting
of his project team. At the meetings he invites representatives of the construction company, the facilities manager
from Friendly Medical Center, the Director of Security,
and other key people as he deems necessary. The meetings
are scheduled every Friday at 1:00 pm and last not more
than 1 hour. No matter who is or is not there, Kyle starts
the meetings exactly at 1:00 pm. Kyle developed the following standing agenda:
1.
2.
3.
4.
Review schedule and budget as of todays date
Review schedule and budget for next 2 weeks
Issues impacting schedule or budget
Next steps and action items to be completed
The construction project update presented at the
April 11, 20X1 meeting is shown on the next page.
After each meeting the construction project manager
emails the minutes of the meeting and the action item list
generated to each member of the Construction Project
team. He also sends the information to Fred Splient, the
president of Friendly Medical Center, as well as to each
member of the ALF Project Steering Team.
Following the update is the most recent copy of the
action items generated at the 4/11/X8 construction project meeting.
Upon reading the minutes and action items from the
weeks meeting, Fred got quite angry. Fred read the minutes every week and would immediately phone Kyle to ask
why certain decisions still had not been made. This week
he wanted to know why the location of the security panel
had not been picked out yet, and what the hair salon issue
was about. Kyle decided that these matters would be better
discussed face to face. He went to Freds office.
Kyle proceeded to explain to Fred that the Director of
Security, Frank Geagy, had not attended the construction
project update meeting in weeks. Kyle said that Frank
informed him that in light of the cost cutting going on in
the hospital, he is short staffed and cannot hire a new
security guard. Frank states that he personally has to cover
shifts during the time when the update meetings take
place. Kyle told Fred that he was not comfortable making
the security panel decision without the head of securitys
input, and that Frank has not returned his phone calls or
answered his emails. Fred Splient proceeded to tell Kyle in
a very loud and angry voice, That guy is not short staffed
S
E
and is not busy covering anyones shift. Who does he think
he is? Fred instructed Kyle to tell Frank to answer the
contractors questions immediately or the decisions would
be made for him.
Kyle said he would do so and then changed the subject.
He told Fred that they were still waiting for the city officials to approve the parking lot construction permit.
Friendly Medical Centers legal officer estimated that it
would take 810 weeks to hear back on approval. Kyle
allocated that amount of time in the schedule.
Kyle received notice from Fred to proceed with the
parking lot construction on January 11, 20X8. On
February 9, he submitted the application for a permit, complete with appropriate plans and descriptions of the proposed lot, and allocated 10 weeks to wait for the county to
notify him. He expected approval on or before April 19
and scheduled construction to begin April 20. Privately, he
doubted he would hear from the county by his target date.
The lot would take 3 weeks to build, 2 weeks to install
the lighting and add landscaping, and 1 week to pave and
stripe. The plot had to be completed by the end of June so
that parking spaces would be available when Marketing
wanted to begin showing the facility to potential residents.
This was a tight schedule, but the marketing people
insisted that residents had to begin preparing for this kind
of move at least a month before they took residence.
Potential residents needed to see the facility, get familiar
with apartment layouts, and they needed a place to park.
Also, Marketing insisted on having some occupancy by
the opening date.
Kyle told Fred that Legal was calling the county weekly
to follow up. Fred wanted to know why the parking lot
construction was not outlined on the project plan for facility construction. Fred asked Kyle to add it to the Gantt
chart and to do a what?if analysis on the assumption that
the county did not respond until May 1. Fred also wanted
to know the latest date that they could be notified and still
meet a June 15 deadline for completion of the lot.
As Kyle was leaving Freds office, Fred asked him about
the hair salon. Kyle explained that the COO and VP of
Marketing had come up with an idea to build and operate
a hair salon in the facility for the residents. They thought
this might be a great selling point that could generate revenue. They came to Kyle just 2 months ago and asked him
to include a hair salon on the first floor of the facility. Kyle
explained that he did not have enough information to be
able to determine the impact this would have on the construction schedule or the cost of this addition. Fred listened and then wondered if the members of his team had
done any analysis to determine if this was a good idea or
not. Fred told Kyle he would get back to him on that one.
He then made a phone call to the COO and VP of
Marketing.
264
Building ready for residents
11
Project Manager: K. Nanno.
Construction complete
10
06/05/X8
06/04/X8
06/04/X8
First 45 units ready for residents 05/01/X8
Remaining 57 units (light &
heavy) ready to prepare for
occupancy
05/01/X8
07/12/X7
07/12/X7
8
Phase 4 ? Interiors
6
9
Phase 3 ? Enclosure
5
04/19/X7
First 45 (light?assisted) units
ready to prepare for occupancy
Phase 2 ? Structure
4
03/01/X7
03/01/X7
03/01/X7
Baseline
Start
7
Phase 1 ? Foundation &
Excavation
Facility construction
2
3
Construction & furnishings
Task Name
1
ID
Assisted Living Facility
Construction Project Update
as of 4/11/X8
Baseline
Finish
NA
NA
NA
NA
NA
07/30/X8
06/04/X8
06/04/X8
06/25/X8
05/01/X8
08/01/X7 06/04/X8
08/01/X7 01/15/X8
05/24/X7 09/22/X7
03/01/X7 07/11/X7
03/01/X7 06/04/X8
03/01/X7 07/30/X8
Actual
Start
NA
NA
NA
NA
NA
NA
01/15/X8
10/09/X7
08/01/X7
NA
NA
Actual
Finish
8 wks
0 days
0 days
8 wks
0 days
234 days
134 days
113 days
95 days
329 days
369 days
Baseline
Duration
0 wks
0 days
0 days
0 wks
0 days
139 days
120 days
99 days
110 days
285.12 days
278.76 days
Actual
Duration
8 wks
0 days
0 days
8 wks
0 days
95 days
0 days
0 days
0 days
57.88 days
104.24 days
Remaining
Variance
0 wks
0 days
0 days
0 wks
0 days
0 days
?14 days
?14 days
15 days
14 days
14 days
Dur.
Variance
14 days
14 days
14 days
14 days
14 days
14 days
0 days
11 days
15 days
14 days
14 days
Finish
Variance
2 65
QUES T IO NS
Friendly Assisted Living Facility Construction
coordination meeting 4/11/X8
ACTION ITEM LIST
Date
Initiated
Item
Date
Required
Date
Resolved
Required
From
Provide notice to proceed on
parking lots
01/10/20X8
ASAP
02/11/20X8
St. Dismas
Provide PS. # for designer to
purchase accessories
11/9/20X7
12/1/20X7
02/8/20X8
St. Dismas
What are the security
requirements? There are fire
doors, and they do not have
locks. We have rough?in for
card readers, but no electric
hardware.
11/9/20X7
12/1/20X7
Lighting reviewwill exterior
lighting in addition to the
building mounted lights be
required?
12/14/20X7
03/15/20X8
Location of security panel
09/28/20X7
ASAP
Room number style and
placement
01/18/20X7
01/27/20X8
Parking lot permit
02/9/20X8
Fire alarm connection to
hospital panel
St. Dismas
Security
03/15/20X8
Comments
Proposal to St.
Dismas 1/18/X7
Cost proposal to
St. Dismas 1/13/X7
St. Dismas
lighting
consultant &
electrician
St. Dismas
security
02/11/20X8
St. Dismas
designer
Part of signage
discussion
ASAP
Contractor
Permit application
2/9/20X8, waiting
for City to approve
02/11/20X8
ASAP
St. Dismas
electrician
Conduit required
Hair salon decision
02/11/20X8
ASAP
St. Dismas
Updated fire alarm drawings
02/7/20X8
07/1/X8
Contractor &
electrician
QUESTIONS
1. What do you think the construction project manager
should have done when the Director of Security
stopped attending the project meetings?
2. Do you think it is an effective communications tool
to send the construction project meeting minutes to
the ALF steering team and the President? Support
your answer.
3. How much time has to be made up for the original,
baseline schedule to be met?
4. Develop a plan and draw a Gantt chart for the
Parking Lot phase of the project as originally planned
by Kyle. Answer Freds questions.
5. What information does Fred need to make a decision
about building a hair salon?
266
CH AP T ER 7 / MON ITOR ING A ND C ONT ROL L ING T H E P R OJE CT
C
A
Palmstar Enterprises, Inc.
Palmstar Enterprises, a leading manufacturer of tablet
computers, is currently in the process of developing its
next generation device, the model 2000HD. A key feature
of the 2000HD is its high definition display. According to
the original project schedule, the 2000HD is to be released
1 month from now.
Because the amount of time required to convert the
existing software to capitalize on the high definition
display was significantly underestimated, the project has
fallen behind schedule. The project manager estimates
that without additional resources, the development project
will be 3 months late. He has also estimated that increasing
S
E
the projects budget of $3 million by 30 percent would permit the project to be completed on schedule. The added
budget would be used primarily to staff the project with
additional software engineers.
If released on schedule, first quarter demand for the
2000HD is forecast to be 200,000 units at an initial price
of $450. Demand data for similar products suggest that
unit sales will increase 5 percent per quarter over the products 3?year life. Despite pricing pressures in the market,
accounting data indicate that Palmstar is able to maintain
a 20 percent contribution margin to profit and overhead
through continuous process improvements and efficiencies accruing from producing in larger volumes.
QUESTIONS
1. What has a larger impact on Palmstars profits: delaying the 2000HDs introduction by 3 months or
increasing the projects budget by 30 percent?
2. Are there other factors you would consider in addition to profit?
C
A
Peak Lighting, Inc.
Peak Lighting, Inc. develops stages, lighting systems, and
special effects for the concert tours of major musical acts.
Recently, they were approached by Bullwhip, a popular
band, to develop the stage, lighting, and special effects for
its upcoming tour.
The project to develop the stage, lighting, and special
effects for a concert tour progresses through four major
phases. In the first phase, which lasts about a week, Peak
develops a sound track for the concert based on the song
list the band provides it for the tour. Using the sound
track, Peak employees develop a synchronized lighting and
special effects show on a computer that allows them to
view an animated stage with the lighting and special
effects as the sound track is being played.
In the second phase, the materials needed for the stage,
lighting, and special effects are ordered from outside suppliers. The lead time for receiving these materials is
4 weeks, and during this period the project team members
are assigned to other projects.
3. What should Palmstar do? Why?
4. How generalizable do you think the results of your
analysis in this particular case are to other situations?
S
E
Once all the materials arrive, the third phase involves
constructing the stage with the lighting and special effects.
Also, writing the computer code to control the lighting
and special effects is done in the third phase. This phase
takes 3 weeks.
In the final phase, which takes a week, the lighting and
special effects are tested and enhanced. The total cost of
the Bullwhip project is estimated to be $600,000 of which
$400,000 is for the stage, lighting equipment, and special
effects, and $200,000 is for labor costs.
Eric Page was recently hired as Peaks VP of Operations.
All the project managers that oversee the stage and lighting projects report to Eric. Prior to joining Peak Lighting,
Eric served as a project manager for a leading management
consulting firm for 10 years. Based on his extensive project
management experience, one of the first things Eric did in
his new role as VP was implement a formal project reporting
system that would help him monitor the progress of the
projects under way.
The Bullwhip project had been underway for 5 weeks,
and all the materials had arrived. The project team was now
2 67
B IB LIOG RA PHY
ready to start the third phase of the project and construct
the stage with the designed lighting and special effects.
In reviewing the most recent progress report for the
Bullwhip project and based on his project management
experience, Eric became gravely concerned. According to
the report, the project had an earned value of $120,000
based on the project manager Jimmy Rushs estimate that
20 percent of the project had been completed. In further
studying the report, Eric observed that the planned value
and actual costs incurred were both $440,000.
Based on his concern, Eric decided to walk down the
hall to Jimmys cubicle and discuss his concerns related to
the progress on the project.
Eric began:
I just reviewed the progress report for the Bullwhip project,
and I am very concerned that the project is falling way
behind schedule. Based on my review, it appears there are
very significant cost and schedule variances. As you know,
we have a hard deadline for completing the project as the
Bullwhip needs everything fully operational 2 weeks prior
to the start of their tour so they can rehearse with it.
Jimmy responded:
To be perfectly honest, I dont know much about schedule
and cost variances but I do have a great deal of experience
managing these projects. Again, I dont know how you calculated the variances you mentioned, but in my view we
are exactly where we should be.
To this Eric replied:
I dont see how you can possibly think the project is on
track when it has an earned value of only $120,000 and
the planned value by this point in the project is $440,000?
And I am equally disturbed you dont understand basic
project management concepts such as earned value.
Later that day, Jimmy shared his frustration about his
new boss with one of the project team members.
Eric really chewed me out today. He questioned my
ability to manage a project. I wonder if he even understands the nature of these projects. Does he even get
it that two thirds of the project costs are for materials
and that these costs are incurred in the early part of
the project?
QUESTIONS
1. Calculate the schedule variance and cost variance for
the Bullwhip project.
2. Does Jimmys point about the material costs have
merit? If so, does this have any implications for the
way the earned valued is calculated at Peak?
3. Who is right about the status of the project?
Eric or Jimmy?
4. What advice, if any, would you offer Eric related to
his new role of VP of Operations?
BIBLIOGRAPHY
Ackoff, R. L. Beyond Problem Solving. Decision
Sciences, April 1974.
Adams, J. R., and L. L. Adams. The Virtual Project:
Managing Tomorrows Team Today. PM Network, January
1997. (An excellent brief discussion that covers the nature
of virtual projects and some of the communication methods allowing their proliferation.)
Barr, Z. Earned Value Analysis: A Case Study. PM
Network, December 1996.
Byrne, J. Project Management: How Much Is Enough?
PM Network, February 1999.
Christensen, D. S. A Review of Cost/Schedule Control
Systems Criterion Literature. Project Management Journal,
September 1994. (This study of military projects notes
that after a project is 1520 percent complete, its total CPI
changes by less than 10 percent and overruns worsen. This
article is briefly noted in Flemming and Koppleman, 1996.)
Dean, B. V. Evaluating, Selecting, and Controlling R&D
Projects. New York: American Management Association
Research Study 89, 1968.
Flemming, Q. W., and J. M. Koppleman. Forecasting the
Final Cost and Schedule Results. PM Network, January
1996. (This is one of five excellent, instructional articles
on earned value by these authors. They appeared in PM
Network between January 1994 and May 1996.)
Gupta, V. K., and D. J. Graham. A Customer Driven
Quality Improvement and Management Project at
Diamond Offshore Drilling. Project Management Journal,
September 1997.
Ibbs, C. W., and Y.?H. Kwak. Benchmarking Project
Management Organizations. PM Network, February 1998.
(This article discusses the development of a tool for finding and assessing the best managerial tools for project
management.)
268
CH AP T ER 7 / MON ITOR ING A ND C ONT ROL L ING T H E P R OJE CT
Ingram, T. Client/Server, Imaging and Earned Value: A
Success Story. PM Network, December 1995.
Meredith, J. R., and S. M. Shafer. Operations and Supply
Chain Management for MBAs, 6th ed. New York: John
Wiley, 2016.
Nixon, T. R. Project Management at the New Parliament
House, Canberra. Project Management Journal,
September 1987.
PMI, Lack of Support, PM Network, January 2005.
PMI Standards Committee. A Guide to the Project
Management Body of Knowledge, 5th ed. Newton Square,
PA: Project Management Institute, 2013.
Reith, W. D., and D. B. Kandt. Project Management at
a Major Automotive Seating Supplier. Project Management
Journal, September 1991.
Thamhain, H. J. Best Practices for Controlling
Technology?Based Projects. Project Management Journal,
December 1996. (A fine analytical study of finding and
assessing the best practices for controlling high?
technology projects. It not only finds the best control
practices, but also generates a benchmark to which any
firm can compare its practices.)
Toney, F. What the Fortune 500 Know about PM Best
Practices. PM Network, February 1997.
Wu, C., and G. Harwell. The MUNI Metro Turnback
Project. PM Network, May 1998.
C
H
A
P
T
E
R
8
Evaluating and Closing the Project
We now come to the exciting final stage in any projectwitnessing the result of all our
project efforts! This usually consists of two sets of activities: evaluating the result of our
efforts and then closing down the project. As we will see, there are many ways to do both,
some relatively formal, some quick and dirty, and some rather casual. We discuss evaluation first, in the generic sense, and then discuss a very specific and often formal type of
evaluation known as the project audit. We contrast the project audit with the more
commonly recognized financial audit. We then describe the audit process, the audit
report, and give some advice for conduction such an audit.
Following this, we discuss various ways of closing out the project, including the possibility of early closure which can occur for a variety of reasons such as a reduced market
need for the output or a low expected return on the investment. Four major types of
closure are by extinction, where the project was either successfully completed or failed
(or expected to be a failure); by addition, where the project output is added to the
organization in whole, as with a new plant; by integration, where the project output
is distributed throughout the organization, as with a software upgrade. However, there
are some interesting vari…
Purchase answer to see full
attachment
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.