PROJECT MANAGEMENT (EARNED VALUE ANALYSIS) Assignment 6

Construction Scheduling

Assignment 6

Don't use plagiarized sources. Get Your Custom Essay on
PROJECT MANAGEMENT (EARNED VALUE ANALYSIS) Assignment 6
Get an essay WRITTEN FOR YOU, Plagiarism free, and by an EXPERT! Just from $10/Page
Order Essay

Suggested format: Times New Roman 12 points, single spaced, 1” margin all around, APA style

for references

Note: All assignments will be checked for plagiarism using SafeAssign. The similarity index

should not be greater than 35% on the report. You should always provide references at the end.

LEARNING OBJECTIVE:

After successfully completing this assignment, students will be able to:

• Perform Earned Value Analysis

• Estimate the status of the project progress quantitatively

 

 

 

Q1. The following depicts a one-year schedule for a project.

 

After three months on the job (July 1), the contractor concluded that 20% of Activity F

(Activities A, B, and D are completed) was completed, 80% of Activity C was completed, and

40% of Activity E was completed. The project has cost the contractor a total of $535. For this

project, using earned value concepts determine the schedule variance and the cost variance. State

if the project is over or under budget and if it is ahead of or behind schedule. 40 points

 

Q2. Please follow the instructions below to update the given Project schedule for Earned

Value Analysis. 60 points

 

The attached MS Project file contains the relationship between activities, estimated durations,

created resources with the maximum amount of resources available together with their estimated

costs, resources assigned to activities as required. You can do the earned value analysis as you

have all the above-mentioned details in the MS Project file.

 

The following are the steps to run in MS Project and update the schedule:

 

1. Start by setting a baseline go to <Project, Set Baseline, choose Baseline, OK>.

 

You need to set a baseline so that you can compare it with your up-to-date schedule later in the

project. In a baseline information is stored in a snapshot of the project including start dates,

finish dates, durations, costs, and amount of work.

 

2. The next step is to set a status date go to <Project, Status Date, choose 9/27/2020>.

 

 

 

This is the date in which you are updating project progress, by default it will show actual date,

you should change it accordingly.

 

3. Following you can update the project by updating the tasks’ progress. On ideal conditions,

activities having a satisfactory progress should have completed the amount of work as planned.

Project should be updated on a weekly basis.

 

Go to <Project, Update Project, Set 0% – 100% complete>

The Gantt chart will show progress bars on the activities.

 

4. But you want to introduce some changes to the project assuming that you are delayed on some

tasks. You can update progress for each activity individually or for summary activities. Proceed

as follows:

 

<On the Gantt chart view, Task, information details> OR double click the particular

activity and under the general tab you can change the completed work value in percentage.

a. Phase 1 task 1: 100% complete

b. Phase 1 task 2: 100% complete

c. Phase 1 task 3: 100% complete

d. Phase 1 task 4: 70% complete

5. Next you want to introduce some changes to the budget:

 

All the labor and equipment costs have been increased by 20% from the estimated to the actual

costs. <Introduce these changes in the Resource Sheet>. Increase all the standard rate value

by 20% in the resource sheet.

 

6. You can add now two more columns to the work sheet: Baseline Cost and % Complete.

 

<Add new Column, baseline cost>

<Add new Column, %complete>

 

You can proceed now to Earned Value analysis:

 

7. By using the Reports tool, you can obtain the Earned Value curves or the actual values from

the Visual Reports and from Reports respectively.

 

Go to <Report, Visual Reports, Earned Value over Time, Weekly, OK>

Go to <Report, cash flow report>

 

 

ABOUT EARNED VALUE:

 

 

 

• BCWS (Budgeted Cost of Work Scheduled): Shows how much of the budget should have been spent according to original planned or baseline.

• BCWP (Budgeted Cost of Work Performed): How much of the task’s budget should have been spent, given the actual duration of the task?

• ACWP (Actual Cost of Work Performed): Shows actual costs incurred for work already performed by a resource on a task.

• CV (Cost Variance) = BCWP – ACWP : (-) Over Budget or (+) Under Budget

• SV (Schedule Variance) = BCWP – BCWS: (-) Behind Schedule or (+) Ahead of Schedule

• EAC (Estimated at Completion): Forecast of the total actual costs required to complete the project.

• BAC (Budgeted at Completion): Original cost estimate.

• VAC (Variance At Completion) : Forecasted Cost Variance

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.