Segmented construction contract
On 1 January 2013, entity A entered into a contract to construct a building on a piece of land it has acquired and, when construction is complete, to deliver the entire property to a customer. A applies the percentage of completion method to account for contract revenues and expenses. The relative percentage of cost incurred is considered a reliable method for measuring the progress of the contract.
Construction has commenced and at the end of the reporting period (31 December 2013) total construction costs incurred amount to €2m.
Entity A considers that the amount of revenue in the contract attributable to the construction is €8.5m and the amount to the sale of land is €2.5m.
The percentage completion of the construction contract is 25% – calculated as €2m costs incurred as a proportion of the €8m estimated total cost of construction.
Accordingly, as at 31 December 2013 the following amounts are recorded:
| Revenue | (€8.5m >c 25%) | €2.13m |
| Contract expense | €2.00m | |
| Gross amount due from customer | (Revenue of €2.13m) | €2.13m |
| Inventory | (Cost of the land) | €2.00m |
part one For this assignment you are to to watch: Shattered Glass Write a two…
Standard Project - WebServers. Instruction attached. Need all requirements, you do not have to make…
Read classmates post and respond with 100 words:The International Categorization of Diseases, Tenth Revision, Clinical…
Most Americans have at least 1 issue that is most important to them. Economic issues…
For this assignment, you are the court intake processor at a federal court where you…
Use a standard outline format to lay out how you are going to write your…